LA Metro has provided us an update of upcoming construction work activities being planned in the area. After the completion of the current freeway roadway restriping activities and placement of concrete barrier along the freeway, major construction activities are in anticipated in the area soon.
Project Background: The I-105
As part of construction of this project, the following locations along the I-105 freeway will soon undergo construction to accommodate the improvements provided by the I-105 ExpressLanes Project.
- Westbound between Standford Ave and Avalon Blvd – anticipated start mid-late March 2025
- Eastbound between Avalon Blvd and Standford Ave – anticipated start mid-April 2025
- Eastbound I-105 between Main St and San Pedro St – anticipated start late April
The work activities at these locations will include the following:
- Soundwall demolition
- Soundwall reconstruction
- Excavation and grading
- Roadway pavement construction
- Landscape removal/restoration
This work is anticipated to include the following details:
- Mostly day-time work hours anticipated
- Most work conducted behind k-rail (concrete barriers)
- Construction access from the freeway
LA Metro will work with local stakeholders and residents to share additional information including schedule, duration, and work activity. If you have any questions or would like additional information, please don’t hesitate to reach out.